Community Updates - February 9, 2012
Good afternoon,
During our last Resident's Representative Meeting, we committed
to providing the community with an overview of the upcoming
construction phases for 30 Weston Road.
We have outlined each phase of site activity below, including a
brief description of the type of work we'll be undertaking and the
approximate timelines that we're anticipating.
Please see below the current schedule:
Approximate Timing: Spring/Summer 2012
Description of Activity: Post Earthwork
Compaction
Approximate Timing: Spring/Summer 2012
Description of Activity: Civil work, consisting
of construction of underground storm, sanitary, water and
electrical systems and assessment of need for brief, follow-up
dynamic compaction. Note: As committed, we will provide the
community with advance notice if any dynamic compaction is
required.
Approximate Timing: Spring/Summer 2012
Description of Activity: Commence construction of
retaining wall
Approximate Timing: Summer 2012
Description of Activity: Commence construction of
buildings and parking structure on south side of site
Approximate Timing: Fall 2012
Description of Activity: Commence construction of
buildings and parking structure on north side of the site
Approximate Timing: Spring/Summer 2013
Description of Activity: Surface work, including
paving and landscaping
Approximate Timing: Spring/Summer/Fall 2013
Description of Activity: Off-site work including
turning lanes and road improvements
We remain committed to providing consistent updates on the work
taking place on the site. Going forward, we will send a monthly
community update. As we move through the construction
program, these updates will include any modifications to the
scheduled timing and activities, so that you consistently have a
clear sense of the work taking place.
We will continue to monitor this email address regularly and are
happy to provide additional information, should you have any
questions.
Sincerely,
Mike and Stefan, Trinity Development Group